The Endless Reminders Trap: Why Settlement Talks Cannot Save a Time-Barred Arbitration Claim
- Apr 20
- 3 min read

B and T AG v. Ministry of Defence | Supreme Court of India | Arbitration Petition No. 13 of 2023 | Decided on 18.05.2023
In a significant ruling on limitation law in arbitration, the Supreme Court of India dismissed a petition for appointment of an arbitrator filed by B and T AG, a Swiss arms manufacturer, against the Ministry of Defence. The Court held that the petitioner's claims were hopelessly time-barred, reaffirming that ongoing bilateral negotiations and the exchange of reminder letters do not extend or pause the three-year limitation period under Article 137 of the Limitation Act, 1963.
Background
In 2012, the Ministry of Defence awarded a contract to B and T AG for the supply of 1,568 Sub Machine Guns. Disputes arose in 2016 when the Ministry encashed a warranty bank guarantee and deducted liquidated damages worth approximately Euro 201,793.75, citing delays in supply. The final deduction was made on 26 September 2016.
Despite this, the parties continued exchanging communications and attending meetings between 2016 and 2019. The petitioner invoked arbitration only on 8 November 2021, more than five years after the cause of action arose, and filed the Section 11(6) petition before the Supreme Court in February 2023.
The Legal Question
The Court framed the central question as whether time-barred claims can be treated as live claims capable of being referred to arbitration. The petitioner argued that the contract's bilateral discussions clause under Article 21.1 kept the limitation clock paused for as long as negotiations continued, and that the "breaking point" was only reached in September 2019. The Ministry countered that the cause of action crystallised on 26 September 2016, when the liquidated damages were finally deducted, and the three-year window expired on 25 September 2019, well before arbitration was invoked.
What the Court Held
A bench of Chief Justice D.Y. Chandrachud and Justice J.B. Pardiwala, with the judgment authored by Justice Pardiwala, rejected the petition on the following grounds.
First, on the breaking point, the Court held that the encashment of the bank guarantee and the final deduction of liquidated damages on 26 September 2016 was the breaking point for the purposes of limitation. This was a positive, unequivocal act by the Ministry that crystallised the cause of action. The letter dated 24 February 2016 itself indicated that the dispute had surfaced as far back as October 2014, when the petitioner had submitted its justifications. The Court held that the bald assertion of continuing negotiations till 2019, without a specifically pleaded and documented negotiation history, was not sufficient to shift the breaking point.
Second, on the effect of bilateral discussions, the Court distinguished the Geo Miller principle from the facts here. While Geo Miller v. Chairman, Rajasthan Vidyut Utpadan Nigam Ltd. [(2020) 14 SCC 643] permits exclusion of bona fide pre-arbitration negotiation periods for computing limitation, this exclusion applies only where the entire negotiation history is specifically pleaded and placed on record. Mere reliance on a bilateral discussions clause in the contract, without substantiating the timeline and substance of those discussions, will not suffice.
Third, on the continuous running of time, the Court relied on Section 9 of the Limitation Act, which provides that once time begins to run, no subsequent disability or inability stops it.
Relying on BSNL v. Nortel Networks [(2021) 5 SCC 738], the Court reiterated that claims which are ex facie time-barred can and should be rejected at the Section 11 stage itself.
The Court, relying on Justice Bachawat’s formulation, held that limitation in arbitration runs from the accrual of the “cause of arbitration”, i.e., when there is a clear and unequivocal denial of the claim. An application under Section 11 is governed by Article 137 of the Limitation Act, 1963 and must be filed within three years from the date the right to apply accrues; once this point is reached, the claimant cannot defer invocation of arbitration beyond the prescribed period.
Conclusion
In conclusion, the Supreme Court in B and T AG v. Ministry of Defence leaves little room for doubt on the consequences of delay. While rejecting the petition, the Court observed, “the case on hand is clearly and undoubtedly, one of a hopelessly barred claim, as the petitioner by its conduct slept over its right for more than five years.” The ruling reinforces that arbitration cannot be invoked to resurrect stale claims, and that once limitation has run its course, the Court will refuse reference at the threshold.
Delay defeats justice. This judgment makes that principle concrete.
_edited.png)



Comments