“Unified Arbitration for Interlinked Contracts: Gujarat High Court Reinforces Consolidated Reference Under Section 11 in the Adani–SMS Carbon Dispute”
- divylotia
- Dec 11, 2025
- 5 min read

Introduction
The question of whether multiple agreements forming part of the same commercial transaction can be referred to a single arbitration continues to arise frequently in complex commercial arrangements. The Gujarat High Court, in its CAV judgment dated 13 September 2024 in Adani Enterprise Ltd v. M/s SMS Carbon & Minerals Pvt. Ltd. (C/ARBI.P/76/2023), delivered a detailed exposition on this issue, reaffirming the principle that arbitration must be interpreted in a commercially pragmatic manner and that courts must give effect to the true intention of the parties rather than adopt a hyper-technical analysis of individual contractual instruments.
This judgment is particularly significant for modern commercial arbitration practice, where large projects are typically documented through several interlinked contracts executed in a short span of time and governed by a central set of General Conditions. The Court’s ruling, grounded in authoritative precedents such as Ameet Lalchand Shah v. Rishabh Enterprises (2018), MTNL v. Canara Bank (2020), and the Delhi High Court’s decision in KGPS Mechanical Pvt. Ltd. v. Cinda Engineering (2024), underscores the judicial trend favouring consolidation where the agreements are correlative and complementary.
The present article examines the factual foundation, the parties’ contentions, the Court’s reasoning, and the broader implications for arbitration jurisprudence in India.
Factual Background
Adani Enterprise Ltd (the petitioner) and SMS Carbon & Minerals Pvt. Ltd. (the respondent) executed a series of ten contracts between 4 April 2022 and 6 April 2022, comprising five coal sale and purchase contracts and five corresponding service agreements relating to imported steam coal stored at Gangavaram Port. All agreements were governed by the General Conditions of Coal Sale and Purchase Contract (GCC) dated 04.04.2022 and the General Terms and Conditions (GTC) dated 04.04.2022, each of which contained a sole arbitrator clause with Ahmedabad as the seat.
The Buyer was obligated to lift the contracted quantities within 45 days from vessel discharge completion (i.e., by 30 July 2022). The Buyer failed to lift the material within the free period and sought an extension of six months. The Seller granted only a two-month extension, expressly without prejudice. The Buyer subsequently failed to lift the entire quantity or furnish the full Earnest Money Deposit (EMD), prompting the Seller to issue notices invoking clauses relating to Buyer’s default and short-closure.
On 10 February 2023, Adani issued a notice invoking Clause 17 of the GCC, proposing a sole arbitrator. The Buyer, in its reply dated 11 March 2023, did not dispute arbitrability but only objected to the name proposed and suggested its own nominee. The parties could not agree on the appointment, leading to this Section 11 petition before the Gujarat High Court.
Issues Before the Court
The primary issue was whether a single petition seeking appointment of one sole arbitrator for disputes arising from multiple agreements was maintainable.
The respondent argued that each contract contained a separate arbitration clause and therefore required separate arbitrations and, consequently, separate Section 11 petitions. Conversely, the petitioner argued that all agreements formed parts of a unified commercial project governed by the same GCC/GTC and were intended to be read together, thereby supporting a single consolidated arbitration.
Contentions of the Parties
Respondent’s Contention
The respondent’s objection centered on maintainability. It submitted that the ten agreements were independent contracts and that a consolidated arbitration could not be initiated merely due to commercial proximity. According to the respondent, separate arbitration agreements mandated separate arbitral proceedings.
Petitioner's Contention
The petitioner countered that the agreements were correlative, complementary, and executed within a narrow timeframe, dealing with the same goods, same destination port, and governed by the same parent documents. The GCC/GTC formed an integral part of all contracts. Moreover, the respondent’s reply to the arbitration notice showed acceptance of arbitration and disagreement only regarding the identity of the arbitrator, not the possibility of a unified proceeding.
The petitioner relied heavily on judicial precedents that emphasize commercial common sense when interpreting arbitration clauses.
Court’s Analysis
The Gujarat High Court undertook a clause-by-clause examination of the GCC, GTC, and individual contracts. It noted that Clause 2 of the GCC expressly stipulates that the GCC and coal sale contracts are “correlative and complementary.” Further, the service agreements incorporated the GTC, which contained an identical arbitration clause.
The Court observed that all contracts:
were executed as part of one cohesive commercial project,
were governed by identical arbitration clauses,
concerned the same coal cargo,
related to the same port (Gangavaram), and
were executed within three days.
The Court held that the intention of the parties was to treat the contracts as interconnected components of a single commercial transaction. The conduct of the parties, especially the respondent’s reply providing its own arbitrator’s name, further demonstrated their mutual understanding that arbitration would be centralized.
Reliance on Precedents
The Court applied three key precedents:
Ameet Lalchand Shah v. Rishabh Enterprises (2018) 15 SCC 678 − where the Supreme Court held that when multiple agreements are part of a unified transaction, even agreements without arbitration clauses may be referred along with others to a single arbitration.
MTNL v. Canara Bank (2020) 12 SCC 767 − which emphasized that arbitration agreements must be construed in a manner that gives effect to the commercial intention of the parties rather than thwarting arbitration.
KGPS Mechanical Pvt. Ltd. v. Cinda Engineering (Delhi HC, 2024) − which permitted consolidated arbitration for several interlinked contracts forming part of the same project, to prevent multiplicity of proceedings and conflicting awards.
Applying these principles, the Court reiterated that arbitration jurisprudence prioritizes practical commercial interpretation over formalistic segregation of contracts.
Conclusion of Analysis
The respondent’s objection was dismissed. The Court held that the multiple agreements “unmistakably form part of the same commercial project” and therefore warranted a single arbitration before a sole arbitrator.
Final Order
The Court allowed the Section 11 petition and appointed Mr. K. A. Puj, Former Judge, High Court of Gujarat, as the sole arbitrator. The arbitration is to be conducted in accordance with the Arbitration Centre (Domestic and International), High Court of Gujarat Rules, 2021. All pending applications were disposed of, and no costs were awarded.
Conclusion & Author’s Opinion
The judgment marks a noteworthy reaffirmation of pro-arbitration judicial philosophy in India. It aligns with the global approach of preventing fragmentation of disputes arising from interdependent agreements within a single project. By interpreting arbitration clauses through the lens of commercial pragmatism and acknowledged contractual integration, the Gujarat High Court has strengthened the efficiency and coherence of arbitral proceedings.
From the author’s perspective, this decision is a welcome development for businesses and practitioners alike. It ensures that parties are not burdened with unnecessary multiplicity of arbitral claims and inconsistent outcomes. It also reinforces the judiciary’s commitment to facilitating streamlined and effective arbitration processes. The ruling will undoubtedly be relied upon in future cases involving layered commercial documentation and will contribute to reducing procedural disputes at the pre-arbitral stage.
_edited.png)



Comments